About the Project
Client:
Nemzeti Sportközpontok (National Sports Centres)
Contractor:
P + W Consortium: Pharos 95 Sportpályaépítő Kft. (consortium leader) and West Hungária Bau Kft.
Architect:
Óbuda Építész Stúdió; Lead Architect: János Plájer
Contract Value:
Net HUF 11,799,254,181
The planned facility will meet UEFA Category 4 and MLSZ Class I "A" standards and will be constructed on the site of the current stadium.
Capacity Details:
Total capacity: 8,200 people
Family section: 1,076 people
Accessible seating: 96 people
Folding seats: 6,550 seats
VIP seats: 408 seats
Skybox capacity: 140 people
Number of skyboxes: 14
Media: 114 people
Parking spaces: 438
14 skyboxes will be located on the 3rd floor of the main building, with the corresponding VIP seats located directly in front of them in the stands. Dedicated catering service (kitchen and bar) is provided for them, as well as on the 2nd floor for season ticket holders and family ticket holders.
Stands:
They enclose the pitch on all 4 sides in an arena layout, fully covered, with no running track.
Schedule:
Site handover: 18 February 2019
Construction deadline and key milestones:
| Construction Activity | Completion Deadlines |
|---|---|
| Stadium reinforced concrete structural works: | 16 September 2019 |
| Completion Deadline: | 13 May 2020 |
| Conclusion of technical handover procedure: | 12 June 2020 |